Bill of quantities

Materials from block to roof

A working quantity survey for the four houses we build. Buy every line from the Wohiri Yard — Aba or Lekki — so the materials on your plot come from us. Cement 50 kg is ₦14,400. A 9″ hollow block is ₦900. Aba market rates (August 2026) plus 20% yard margin. Prices can change. Confirm at the yard before you transfer.

Bungalow

Single-level living. Easy to build, easy to live in.

1 floor
Footprint
150 m²
Floor area
150 m²
Bedrooms
3
Wall height
3.05 m

Materials (block to roof) ₦13,612,980 · ₦13.6m

Compare the four house types
HouseArea9″ blocksCementRoofBill
Bungalow150 m²1830299 bags174 m²₦13.6m
Single terrace240 m²2830501 bags135 m²₦18.4m
Detached duplex400 m²3670745 bags236 m²₦28.3m
Villa560 m²4580982 bags341 m²₦37.8m

Foundation & substructure

Setting out to DPC. Laterite fill, strip footing, foundation blocks.

₦2,271,000

ItemSpecificationQtyRateAmount
Setting-out pegs & lineHardwood pegs, nail, line24 pcs₦350₦8,400
Laterite fillingCompacted under floor84 tonnes₦5,400₦453,600
Concrete 1:3:6 in footingsMix on site10 m³in mix—
Granite ¾″For footing concrete8 tonnes₦26,400₦211,200
Sharp sandFor footing & mortar5 tonnes₦13,200₦66,000
CementDangote / BUA 50 kg60 bags₦14,400₦864,000
9″ sandcrete blocksFoundation courses470 nos₦900₦423,000
DPC150 mm polythene / bitumen felt51 m₦4,800₦244,800

Blockwork

From DPC to roof plate. External 9″, partitions 6″. Includes 8% waste.

₦3,550,200

ItemSpecificationQtyRateAmount
9″ hollow blocks450 × 225 × 225 mm, load-bearing1,830 nos₦900₦1,647,000
6″ hollow blocksInternal partitions1,060 nos₦720₦763,200
CementBlock mortar 1:676 bags₦14,400₦1,094,400
Soft / plaster sandMortar for bedding4 tonnes₦11,400₦45,600

Concrete, columns & slab

Cast columns, floor slab (upper floors), and ground-floor oversite.

₦2,608,560

ItemSpecificationQtyRateAmount
Oversite concrete 1:2:4100 mm on hardcore16 m³in mix—
Column concrete 1:2:412 columns2 m³in mix—
Suspended slab 150 mmNone — bungalow0 m³in mix—
Granite ¾″Columns, slab, oversite16 tonnes₦26,400₦422,400
Sharp sandStructural concrete9 tonnes₦13,200₦118,800
Cement50 kg bags130 bags₦14,400₦1,872,000
Formwork timberMarine board / 1×12 + props74 m²₦2,640₦195,360

Reinforcement

High-yield bars, 12 m lengths. Stirrups from Y10 / Y8.

₦2,124,200

ItemSpecificationQtyRateAmount
Y16 high-yield12 m — columns & main beams42 lengths₦18,500₦777,000
Y12 high-yield12 m — beams & slab mains56 lengths₦10,200₦571,200
Y10 high-yield12 m — distributors & stirrups70 lengths₦7,100₦497,000
Y8 mild / HY12 m — links, extra stirrups36 lengths₦4,550₦163,800
Binding wire25 kg roll4 rolls₦28,800₦115,200

Lintel & ring beam

Concrete lintels over openings, ring beam to take the roof.

₦821,900

ItemSpecificationQtyRateAmount
Lintel / ring-beam concrete1:2:4, 225 × 225 mm4 m³in mix—
Granite ¾″Ring beam & lintels5 tonnes₦26,400₦132,000
Cement50 kg bags33 bags₦14,400₦475,200
Y12 in ring beam4 bars typical12 lengths₦10,200₦122,400
Y10 stirrups150 mm c/c13 lengths₦7,100₦92,300

Roof carcass

Hardwood trusses, purlins, noggins, fascia. Treated against termite.

₦311,400

ItemSpecificationQtyRateAmount
Rafters 2″ × 6″Hardwood, 12 ft, 1.2 m c/c16 pcs₦4,200₦67,200
Purlins 2″ × 3″Hardwood, 12 ft46 pcs₦1,800₦82,800
Tie beams 2″ × 4″Wall plate & ties7 pcs₦2,650₦18,550
Noggins 2″ × 2″ / 2×3Bracing32 pcs₦1,800₦57,600
Fascia 1″ × 12″Hardwood board15 pcs₦3,350₦50,250
Solignum / creosote4-litre tins5 tins₦7,000₦35,000

Roof covering

Aluminium longspan 0.45 mm, ridges, hips, nails. Stops at watertight shell.

₦1,925,720

ItemSpecificationQtyRateAmount
Longspan aluminium 0.45 mmStone / plain, ~1.05 m cover174 m²₦8,400₦1,461,600
Ridge capMatching aluminium14 m₦7,000₦98,000
Hip / valley flashingAluminium20 m₦5,750₦115,000
Eaves filler & flashingFoam + aluminium44 m₦1,800₦79,200
Roofing screws / nailsPack of 100 with rubber4 packs₦4,550₦18,200
Underlay (optional)Sarking felt183 m²₦840₦153,720

Quantities include 8% waste on blocks and 5% on concrete materials. Cement (50 kg) is ₦14,400 and 9″ hollow blocks are ₦900 each — Aba market plus 20% yard margin; prices can change. This schedule stops at a watertight roof — finishes, electrics, and plumbing are a separate bill.